A Product Launch Timeline With Video Review Deadlines

By Oakgen TeamPublished 2 min read

Share
A Product Launch Timeline With Video Review Deadlines

Build the product launch timeline backward from the moment customers can use the release. Lock the claim and capture path before a first cut, leave a review window before the file deadline, and give one person authority to decide what ships if a late bug changes the footage. An edit deadline is meaningful only if the person approving the edit has time set aside.

The example below gives a small SaaS team two working weeks to launch a fictional โ€œGuest approvalโ€ feature. Release day is a Tuesday so the team can monitor it during its normal work week. Use relative days if your calendar differs.

Mark the dates that determine everything else

WhenOwnerWhat needs to be ready
Tโ€“10 working daysProduct leadConfirm release scope, audiences, eligibility, and the supported path the video can show
Tโ€“8Marketing leadApprove one claim, the action for viewers, and a channel list with the required cuts
Tโ€“7EditorRecord a disposable draft from a demo account and test whether the result can be understood silently
Tโ€“6Product leadApprove the demonstrated result and flag UI or copy likely to change
Tโ€“5EditorDeliver first cut with the real interface, short captions, and all open issues in the review link
Tโ€“4Marketing leadConsolidate notes into must-fix items and optional edits
Tโ€“3Product leadApprove the actual app behavior shown. Flag anything missing from staging
Tโ€“2EditorLock the version. Proof captions, contrast, and pause points in the exports
Tโ€“1Marketing leadCheck scheduled posts, landing destinations, fallback assets, and release-day message
TProduct leadVerify real availability and tell marketing whether to release or hold each channel
T+1Editor and marketing leadCheck for playback, caption, and crop reports. Replace affected exports and record the version

Put the specific time next to Tโ€“2, such as โ€œFriday, 2 p.m., captioned exports frozen.โ€ If two people mean different time zones, write both or put the exact time in the calendar invite. Give each review one named owner.

What to do when a late change breaks the cut

Imagine the Send for approval button moves from the toolbar to a menu at Tโ€“1. The affected shot is a six-second screen recording. The editor keeps the source around that action by itself, so it can be recaptured, swapped, and checked against the captions without rebuilding the rest. If the capability itself slips, move the affected video and announcements off the calendar. Prepare a still proof or release note for eligible users only if it shows what actually shipped.

A three-person team can keep one editor, one product approver and one release owner, even when each person holds two jobs. Use the same three approval moments and trim channels instead. Keep one main demo, one landing page, and one announcement. Replace three bespoke social cuts with a still made from the approved recording. Move extra footage to the following week. Reviewers should know what was cut and what decision still needs to happen.

Save the handoff in one place

Add five fields to each launch row. Record the release owner, current export, destination, last check, and fallback. A clean filename means little if automation is still scheduled with the previous attachment. Confirm the file in the actual publishing draft after any replacement. For the edit itself, Oakgen's launch video workflow has a separate script and production schedule.